Across 370 m², EMC carried out rehabilitation and waterproofing works for the metal roof of Al Helw Tower using a reinforced acrylic system to protect the roof against water ingress and weather exposure.
EMC carried out rehabilitation and waterproofing works for the metal roof of Al Helw Tower in Damietta, for Zakaria Al Helw Contracting, covering a total area of 370 m².
The works included treating damaged sections, joints, and vulnerable areas, followed by the application of a reinforced acrylic waterproofing system using fleece and fiberglass to provide comprehensive protection against water ingress and weather exposure.
Site inspection and identification of damaged and vulnerable roof areas.
Cutting and removal of severely deteriorated metal sections.
Installation and fixing of new metal sheets in damaged areas.
Securing loose sheets and open joints using metal fasteners.
Filling joints, gaps, and openings with epoxy putty.
Reinforcement of damaged areas and joints using fiberglass and epoxy coatings.
Treatment of vulnerable areas with fiberglass-reinforced acrylic material.
Reinforcement of roof upstands and corner connections.
Installation of the fleece layer and application of acrylic waterproofing material.
Application of a second acrylic waterproofing coat.
Final inspection and handover following completion of the waterproofing works.