Across 1,900 m², EMC carried out thermal and waterproofing works for Star Feed’s metal roof using Polyurethane Foam, including joint and opening treatment followed by a protective coating.
EMC carried out thermal and waterproofing works for the metal roof of Star Feed in New Salhia, for El Tokhy Group, covering a total area of 1,900 m².
The works included treating joints and openings around chimneys, cables, and pipes before spray-applying Polyurethane Foam to form a continuous insulation layer, followed by a protective coating against UV exposure and weather conditions.
Inspection of the metal roof and identification of joints and openings.
Measurement of roof surface temperature before insulation.
Sealing and treatment of joints between metal sheets.
Treatment of openings surrounding chimneys, cables, and pipes.
Sealing of fasteners, connections, and vulnerable roof areas.
Surface preparation before insulation application.
Spray application of Polyurethane Foam across the entire roof.
Insulation of areas surrounding chimneys and roof penetrations.
Formation of a continuous thermal and waterproofing layer.
Application of a protective coating over the Polyurethane Foam for UV and weather resistance.
Post-insulation surface temperature measurements to verify thermal performance.
Final inspection and handover.